Trakia Economic Zone – Kuklen

Client: Elektrorazpredelenie Yug EAD (EVN)
Construction of new MV (20kV) and LV (0.4kV) cable power lines with a length of more than 8km, installation of new substations and distribution substations.
Construction of external power supply for the following industrial plants:
- Plant for auto parts “Willi Elbe Automotive“
- Plant for metalworking machines and equipment “Nukon Bulgaria”
- Plant for metalworking machines "Spinner Bulgaria"
- “Odelo Farba” Car lighting plant
Year of completion: 2018 - 2021
Amount: 652,000 BGN